Construction Management - Progress Reports

Construction Management - Progress Reports

Progress Report

The progress report window displays graphs and percentages reflecting the state of progress of every single component of the PV plant for every single flight performed. The components show by it’s component group as below:

Mechanical
  1. Piles
  2. Tables
  3. Modules
Electrical
  1. AC cables
  2. DC cables
Infrastructure
  1. Transformers
  2. Inverters
  3. Roads
  4. Fences
  5. Buildings
  6. Substations
  7. Batteries
The progress report of each component will be showing the percentage and the quantity of each component based on the progress of the project. Users are able to view the following reports:
  1. Overall progress
  2. Predicted completion
  3. Completed items to date
  4. Component progress
If the project is divided into several blocks, the user is also able to select to filter the report by a number of blocks. The blocks are defined by the Client, it can be based on an electrical block, a field, or a large area of the PV site etc.



Overall Progress

This chart shows all the Overall Progress for each component and component group, so that users can understand their general progress. The chart is based on the latest report.

This chart reflects the 3 stages:

  1. Not Started ()
  2. In Progress ()
  3. Complete ()

By clicking the arrow icon on component group, the system will show the overall progress of each component. To understand the progress of each group, move the cursor to the chart and a summary table will appear in a hover window.


The stages correspond to the statuses you find in the legend on the Map tab. Grey () would not be visible on the map, hence the black (). There can be many stages to "In progress" ().



For example, for Cables:
  1. Not started () = Not started ()
  2. In progress () = Breaking ground (), Trench open () and Cable installed ()
  3. Complete () = Trench closed ()
The only exception is for Tables and Modules, which are shown separately on Progress Reports tab but as one item on the Map tab:

Tables

  1. Not started () = Not started ()
  2. In progress () = Main beams ()
  3. Complete () = Table structure complete ()

Modules (they are grouped with tables on the map thus either not started or complete in reporting)

  1. Not started () = Not started (), Main beams () & Table structure complete ()
  2. Complete () = Modules mounted ()

Predicted Completion

This table shows an estimation based on the historical, average rate of progress over all previous events (requires at least 3 events to show the predicted completion date, otherwise date will show as a “-‘’).

Once a component 100% complete, then the predicted completion date will equal the actual completion date.



A straight line is extrapolated forward from the most recent event date to where this line hits "100% completion" to derive the "Predicted completion date". The gradient of this straight line is based on the weighted best-fit of progress at all previous event dates. 



Completed Items to Date

This chart has been created to show:

  1. The % of completed items up to the latest event
  2. The progress of completion over time

Each event date in the construction phase will appear on this chart, whether it has been inputted by the customer (Update Progress tab) or from data collected by drone.

This allows clients to compare these values against their project milestones (Gantt Chart) and timeline, to make sure that the project is on track. Simply by moving the cursor to the date column, a summary of each date will be shown.

As you can see from the screenshot below, the graph presents two types of entries:

  1. Full circle - Data collected by a drone and analysed by Above - Above data


  1. Empty circle - Data added by a customer through the "Update Progress" tab - User data


For example, if the chart shows that on a given date Transformers were 30.3% complete, then that means that 30.3% of the Transformers on site have got the status “Transformers complete”, and that the rest (69.7%) are either at “Not started”, “Breaking ground”, “Foundations laid” or “Equipment mounted”.

This allows clients to compare these values against their project milestones (Gantt Chart) and timeline, to make sure that the project is on track.

Component Progress

These charts allow you to compare work being performed on each component over time, making sure that you see your team’s progress in between each event.

Users can select a range of event dates, to see the amount of work done between each event date within that selection. By moving the cursor to specific progress then the quantity will be shown.






These charts allow you to compare the work being performed between each event. Each of these charts shows the work for a component type (tables, cables etc.). For example, if the “Piles” chart shows the following values between two events:
  1. Drilling complete - 1,540
  2. Piles installed - 726

As you can see from the screenshots below, these charts also represent 2 types of entries:

  1. Full bar - Data collected by a drone and analysed by Above - Above data



  1. "Hashed" bar - Data added by a customer through the "Update Progress" tab - User data




As you can see from the screenshot above, the chart can now also manage negative values.





    • Related Articles

    • Construction Management - Update Progress

      Introduction The Update Progress page allows users to update the construction progress on their own. This enables you to update the construction progress on a daily basis and ensure that you have an accurate and up-to-date progress report on the ...
    • Construction Management- Getting started

      Introduction Drone-based construction management is a very effective solution that provides your team with bird’s eyes insights giving the following benefits: Accessing Construction Management in SolarGain In first place, It is necessary to access ...
    • Construction Management - Annotations

      Annotations The annotation module contains the list of all the saved annotations taken through the whole process of construction. Annotations are listed in 7 different columns: Event Date It specifies the flight date of the construction monitoring ...
    • Construction Management - Map View

      Map View The map section is composed of three different interaction areas: “Map layers”, “Action tools” an “Event date”. Map Layers The map layers, located at the left-hand side, can be turned on/off individually or per group. This way the user can ...
    • Digital Twin - Serial Number Management (Deletion) Tool

      Overview More sites are requiring serial number scanning to provide a unique identifier for each component. SolarGain Mobile (SGM) is used to scan these numbers. There are instances when serial numbers are scanned incorrectly. In the past, a special ...